1 (a) What is outsourcing? What are its advantages and disadvantages?
5 M
1 (b) What is project management? Why is it needed?
5 M
1 (c) Define project. What are the attributes of project?
5 M
1 (d) What is project integration management?
5 M
1 (e) What is relation between MOV, scope and WBS
5 M

2 (a) Explain project procurement management.
10 M
2 (b) What are the methods of budgeting for a project?
10 M

3 (a) Explain the project Scheduling techniques.
10 M
3 (b) Explain IT project risk identification framework.
10 M

4 (a) Explain the various leadership styles.
10 M
4 (b) Explain the project change management plan.
10 M

5 (a) Explain scope management plan.
10 M
5 (b) Explain the project implementation approaches.
10 M

6 (a) Explain project planning framework.
10 M
6 (b) Define critical path. Draw AON diagram and find critical path for
Activity Predecessor Duration in days
A - 2
B A 5
C A 2
D B 5
E B 5
F C 5
G D 1
H D 1
I G 2
J E, F, H, I 1
10 M

Write short note on any two:
7 (a) Resource loading and resource levelling.
10 M
7 (b) Dealing with resistance and conflicts in project.
10 M
7 (c) Project communication plan
10 M