1(a)
Following is the data associated with small construction Project. Draw Network. Calculate event Times. Identify Critical Path, Also determine Values of all types of floats.
Activity | A | B | C | D | E | F | G |
Preceeding Activity | ----- | A | A | A | B | D | C,E,F |
Duration(days). | 5 | 4 | 7 | 5 | 3 | 4 | 7 |
10 M
1(b)
Explain, Henry Fayol's 14 Principles of Management.
10 M
2(a)
Following is the data associated with a small Project.
Determine standard Deviation & Variance of the Project. Also determine the Probability of completing the project at :-
i) Expected duration ii) 3 weeks earlier than expected duraiton
iii) 3 weeks later than expected duration.
Activity | 1-2 | 1-3 | 1-4 | 2-5 | 3-5 | 4-6 | 5-6 |
To(weekss) | 1 | 1 | 2 | 1 | 2 | 2 | 3 |
Tm(weeks) | 1 | 4 | 2 | 1 | 5 | 5 | 6 |
Tp(weeks) | 7 | 7 | 8 | 1 | 14 | 8 | 15 |
Z | -3 | -2 | -1 | 0 | 1 | 2 | 3 |
P(%) | 0.13 | 2.28 | 15.87 | 50 | 84.13 | 97.72 | 99.87 |
Determine standard Deviation & Variance of the Project. Also determine the Probability of completing the project at :-
i) Expected duration ii) 3 weeks earlier than expected duraiton
iii) 3 weeks later than expected duration.
12 M
2(b)
What is Quality control? Explain the role of inspection in quality control
8 M
3(a)
Determine optimum cost of optimum duration for the following data of a project . Indirect Cost of project = Rs. 1000/day.
Activity | 1-2 | 1-3 | 2-3 | 2-4 | 3-4 | 4-5 |
National Duration(days) | 6 | 8 | 4 | 5 | 5 | 7 |
Crash Duration (days) | 3 | 5 | 1 | 3 | 3 | 4 |
Normal Cost (Rs). | 7000 | 4000 | 6000 | 8000 | 5000 | 8000 |
Crash Cost ( Rs) | 14500 | 8500 | 9000 | 15000 | 11000 | 15000 |
10 M
3(b)
What do you understand by "Updating of Project? What information is required while updating? Explain the stepwise procedure of updating.
10 M
4(a)
Table below shows activites, their durations and labour requirements:
Workout daily requirement of carpenters with all activity schedule to start at their EST, LST. Also prepare historgam. Comment which schedule will you prefer &why?
Activity | Duration | Carpenters |
A (1-2) | 8 | 3 |
B (1-3) | 11 | 4 |
C (2-5) | 6 | 2 |
D (3-4) | 5 | 5 |
E(3-5) | 8 | 3 |
F (4-5) | 5 | 3 |
Workout daily requirement of carpenters with all activity schedule to start at their EST, LST. Also prepare historgam. Comment which schedule will you prefer &why?
12 M
4(b)
Explain Resurce Smoothening & Resource Levelling.
8 M
5(a)
Explain the functions of Human Resource Management.
10 M
5(b)
What is accounting? Explain generally accepted principles of an accounting.
10 M
Write short note any five question from Q.6(a, b, c, d, e,f )
6(a)
Job Layout
4 M
6(b)
Work Breakdown Structure
4 M
6(c)
Net Present value
4 M
6(d)
ISO 14000
4 M
6(e)
Time Over-run & Cost Over-run
4 M
6(f)
Contribution of Mr.Taylor.
4 M